Scaffold Inspections: UK Requirements and Best Practices
A scaffold that was safe on Monday can be unsafe by Friday. Ties get removed so a window can be fitted. Boards are lifted to pass materials through. A storm loosens a base plate on soft ground. None of these show up unless someone looks.
That is why UK law sets clear rules for scaffold inspections. A competent person must inspect a scaffold before it is first used, at least every 7 days while it stays up, and after anything that could affect its safety. On construction work where someone could fall 2m or more, each inspection needs a written report.
This guide is for site managers, principal contractors, facilities managers and trades who work from scaffolds on commercial jobs. It covers the legal rules, who can inspect, what to check, how to record it and the faults inspectors find most often. The same principles apply across the main types of scaffolds, from tube and fitting to system scaffolds.
The Law Behind Scaffold Inspections
Scaffold inspections in Great Britain come under the Work at Height Regulations 2005. Regulation 12 sets out when work equipment for working at height must be inspected, and Schedule 7 lists what the written report must contain. HSE enforces these rules on site.
Alongside the law, the industry works to guidance from the NASC. TG20:21 is the main technical guidance for tube and fitting scaffolds, and SG4:22 covers preventing falls during scaffold work. HSE uses this guidance as the benchmark for good practice, so inspectors check scaffolds against it as well as against the regulations.
Two other documents matter on most commercial sites:
- TG20 compliance sheet. Where a scaffold follows a standard TG20 configuration, the scaffold contractor provides a compliance sheet showing the design limits, such as maximum height, tie pattern and load class. Anything outside those limits needs a bespoke design from a competent designer.
- Handover certificate. When the scaffold is finished, the contractor hands it over with a certificate. It states the load class, what the scaffold is for and any limits on its use. The person taking it over should check it matches the job before anyone works on it.
When a Scaffold Must Be Inspected
The 7-day rule is the one most people know, but it is only one of several triggers. Here is how they fit together.
| When | Who inspects | What you record |
|---|---|---|
| After erection, before first use | Competent person | Written report |
| At least every 7 days while it stays up | Competent person | Written report |
| After a substantial alteration | Competent person | Written report |
| After bad weather, an impact or anything that could affect stability | Competent person | Written report |
| Before each shift | Scaffold user or supervisor | Pre-use check, often logged on site |
After erection. Nobody should use a scaffold until it has been inspected and handed over. This applies to every new scaffold and every new section added to an existing one.
Every 7 days. Seven days is the longest gap the law allows, not a target. If the last inspection was eight days ago, the scaffold is overdue and should not be used until it is inspected again. Busy or exposed sites often inspect more often.
After alterations. Adding a lift, extending a run, moving a loading bay or removing ties all count. So does dropping boards or guardrails to make room for another trade. The altered scaffold needs a fresh inspection before anyone uses it.
After adverse events. High winds, heavy rain, snow and frost can all affect a scaffold and the ground it stands on. So can a strike from a vehicle, a crane load or a telehandler. Inspect before work restarts.
Before each use. Users and supervisors should carry out a quick visual check at the start of every shift. It doesn’t replace the formal inspection, but it catches damage between inspections.
Who Can Carry Out a Scaffold Inspection
The law asks for a competent person. That means someone with the training, knowledge and experience to judge whether the scaffold is safe for its type and complexity. Job title alone doesn’t make someone competent, and nor does being named on a form.
For basic scaffolds, HSE accepts that a non-scaffolder can be competent if they have attended a suitable scaffold inspection course and have the right background experience. A site manager is the usual example. For more complex or designed scaffolds, the inspector needs a higher level of competence to match.
In practice, most commercial sites look for the CISRS Scaffold Inspection Training Scheme (SITS). There are two levels:
- Basic Scaffold Inspection covers standard scaffolds, such as TG20-compliant independent and putlog scaffolds. It is usually a three-day course and is open to scaffolders, site managers, supervisors and others with the right experience.
- Advanced Scaffold Inspection covers complex structures, such as designed scaffolds, cantilevers, loading towers and temporary roofs.
Short awareness courses help site teams spot obvious faults, but they don’t qualify someone to carry out statutory inspections or sign handover certificates on their own. If no one on site has the right competence, ask the scaffold contractor or an independent inspector to carry out the inspections.
What a Scaffold Inspection Covers
Work from the ground up, with the TG20 compliance sheet or design drawing and the handover certificate to hand. Compare the scaffold to what was designed, not to memory. Inspectors usually work through these areas in order.
Foundations and base. Base plates should sit on firm, level ground, with sole boards on soft ground or tarmac. Look for sinking, washout after rain, and anything stacked against or dug next to the standards.
Standards, ledgers and transoms. Standards should be plumb and properly joined. Ledgers and transoms must be present, level and fixed with the right fittings. Check couplers are tight and not damaged.
Bracing. Façade and ledger bracing must match the design. Missing braces are a common fault on scaffolds that have been up for a while, especially where other trades need access.
Ties. Ties hold the scaffold to the building. Check the pattern matches the compliance sheet or design, every tie is in place and tight, and none have been removed or moved. Anchors should have been tested, with results recorded.
Working platforms. Platforms must be fully boarded, with no gaps, trips, broken boards or boards overhanging too far. Boards should be clipped or tied where the design needs it.
Edge protection. Every working platform needs a top guardrail at least 950mm above the platform, with no gap bigger than 470mm between rails and toe boards. Brick guards should be fitted where materials are stacked.
Access. Ladders should be secured, extend about 1m above the landing and have a safety gate at the top. On larger scaffolds, check ladder bays or stair access are in place. Nobody should be climbing the frame.
Loading. The load on each platform must stay within the scaffold’s load class. Loading bays need their own design. Look for pallets of blocks on a light duty scaffold, which is a common way scaffolds become overloaded.
Sheeting, netting and public protection. Sheeting and netting increase wind load, so the scaffold must have been designed with them in mind. Where the public pass below, check fans, debris netting, lighting and barriers are in place.
Incomplete sections. Any part of the scaffold that isn’t ready must be closed off with a physical barrier and warning signs at every access point.
Check the Load Class Against the Work
A scaffold that is safe for painting can fail under pallets of blocks. Every scaffold is designed for a load class, and the handover certificate should say which one. HSE advises treating a scaffold as general purpose (Class 3) unless the scaffold provider tells you otherwise.
| Load class | Maximum load | Typical use |
|---|---|---|
| Class 1, very light duty | 0.75 kN/m² (about 75kg/m²) | Inspection and access only, no materials stored |
| Class 2, light duty | 1.5 kN/m² (about 150kg/m²) | Painting, cleaning and light finishing work |
| Class 3, general purpose | 2.0 kN/m² (about 200kg/m²) | General building work, plastering, light brickwork |
| Class 4, heavy duty | 3.0 kN/m² (about 300kg/m²) | Heavy masonry, blockwork and cladding |
| Class 5 and 6 | 4.5 to 6.0 kN/m² | Special heavy-duty work, designed scaffolds only |
During each inspection, check that the work on the scaffold still matches its class. If the job changes, such as a cladding package starting on a scaffold built for painters, the scaffold contractor needs to review the design before the new loads go on.
Record Each Inspection in Writing
For construction work with a fall risk of 2m or more, every formal inspection needs a written report. Schedule 7 of the Work at Height Regulations sets out what it must contain:
- the name and address of the person the inspection was carried out for
- the location of the scaffold
- a description of the scaffold
- the date and time of the inspection
- details of any defect that could put someone at risk
- details of any action taken as a result
- details of any further action needed
- the name and position of the person who carried out the inspection
The inspector must complete the report by the end of the working period and give a copy to the person it was carried out for within 24 hours. Keep the report on site until the work is finished, then at an office for three months.
Most sites keep reports in a scaffold register, either on paper or in a digital system. Digital registers make it easier to see which scaffolds are due, attach photos and share records with the principal contractor.
Use Scaffold Tags Correctly
Scaffold tags are not a legal requirement, but they are standard practice on commercial sites. A tag holder sits at each access point and shows the scaffold’s status at a glance.
A green insert, signed and dated by the inspector, means the scaffold has been inspected and can be used. A red insert, or an empty holder, means stay off. Always check the date on a green tag. If it is more than 7 days old, the scaffold is overdue and should not be used until it is inspected again.
A tag supports the written report. It doesn’t replace it.
Common Faults Found During Scaffold Inspections
Most failed inspections come down to the same short list. Knowing them helps inspectors and site managers know where to look first.
- Unauthorised alterations. Ties, boards or guardrails removed by other trades to get their work done, then not put back. This is the most common cause of a scaffold becoming unsafe between inspections.
- Missing or loose ties. A scaffold with missing ties can pull away from the building, especially once sheeting is added.
- Sunk or shifted base plates. Often found after heavy rain or when ground near the scaffold has been dug out.
- Missing guardrails or toe boards. Leaves people exposed to falls and anyone below exposed to falling materials.
- Gaps or damaged boards. Creates trip and fall-through risks on the platform.
- Materials stacked beyond the load class, or concentrated in one bay.
- Climbing the frame. A sign that the access isn’t where people need it.
- Overdue inspections. Scaffolds still in use after the 7-day limit has passed.
What to Do When a Scaffold Fails Inspection
A scaffold that fails inspection is out of use until the fault is fixed and it passes again. Stop work on the affected section and clear everyone off it. Replace the green tag with a red one, or remove the insert, and put up barriers and signs at every access point.
Record the defect in the report and tell the person in charge of the site. Only the scaffold contractor, or other competent scaffolders, should carry out the repair. Site trades should never fix a scaffold themselves, even if the fault looks simple. Once the repair is done, a competent person must inspect the scaffold again before anyone uses it.
How Mobile Towers Differ
Mobile access towers follow the same Work at Height Regulations, but their inspection is set up differently. Towers are built from prefabricated parts to the manufacturer’s manual, and inspectors usually train through PASMA rather than CISRS. The checks focus on castors, stabilisers, braces and platforms rather than ties and tube and fitting joints.
Many commercial jobs that don’t need a full scaffold, such as ceiling work, M&E installs and internal fit-out, use mobile towers through scaffold tower hire instead. Their height limits are also different, and the maximum height of a scaffold tower depends on whether it stands indoors or outdoors. The full checklist and record rules for towers are set out in the guide to scaffold tower inspection.
Build Scaffold Inspections into Your Site Routine
Inspections only work if they happen every time. Keep the system simple enough that it doesn’t depend on one person remembering.
Give every scaffold a reference number and keep a register with its location, load class and next inspection date. Tie the 7-day inspection to something that already happens weekly, such as the site meeting. Make sure the scaffold contractor knows who to contact if a fault is found, and agree response times for repairs in the contract.
Brief every trade at induction that only scaffolders alter the scaffold, that they must check the tag before climbing, and that damage must be reported straight away. On long programmes, plan the inspection time and cost into the schedule. A 12-week job means at least 12 formal inspections for every scaffold on site.
Scaffold Inspection FAQs
How often does a scaffold need to be inspected?
Before first use, at least every 7 days while it stays up, and after any alteration or event that could affect its safety, such as high winds or an impact.
Who can sign off a scaffold inspection?
A competent person with the right training and experience for that scaffold. For basic scaffolds this can be a trained site manager. For complex or designed scaffolds, it is usually a CISRS Advanced Scaffold Inspection card holder.
Is a scaffold tag a legal requirement?
No. Tags are good practice and show status at a glance, but the legal requirement is the inspection and the written report.
Who is responsible for scaffold inspections on site?
The person in control of the scaffold, usually the principal contractor or the employer whose workers use it. They can ask the scaffold contractor or an independent inspector to carry out the inspections, but the duty to make sure they happen stays with them.
How long do scaffold inspection records need to be kept?
On site until the work is complete, then at an office for three months.
Can a trade use a scaffold that was inspected 8 days ago?
No. Once 7 days have passed, the scaffold is overdue and should not be used until a competent person has inspected it again.