Scaffold Tower Inspection: UK Requirements and Best Practices in 2027

A tower that passed last week can fail today. Clips work loose. Storms shift stabilisers. Braces go missing when another trade borrows them. Regular inspection catches these faults before anyone climbs.

UK law is clear. A competent person must inspect your tower after assembly and before first use. On construction work where someone could fall 2m or more, they must inspect it at least every 7 days. Bad weather, an impact or an alteration also needs a new inspection. Users should check the tower before climbing each day.

These rules come from the Work at Height Regulations 2005 and HSE guidance. This guide is for site managers, supervisors and contractors who run towers on commercial jobs. It covers when to inspect, who can do it, a step-by-step checklist, what to record and what to do when a tower fails.

Scaffold Tower Inspection at a Glance

When Who inspects What you record
After assembly, before first use Competent person Written report
At least every 7 days (2m+ fall risk) Competent person Written report
After bad weather, impact or alteration Competent person Written report
Before each shift Tower user Pre-use check

Tags show a tower’s status at a glance. On their own, they only replace the written report if they hold all the details the law asks for.

Know the Three Levels of Tower Checks

Site teams often mix up the different checks. Each one has a different job, and none replaces the others.

  • Component check. Done by the build team before assembly, when parts arrive or come out of storage. No written record is needed, but any damaged part should be set aside and reported.
  • Formal inspection. Done by a competent person after assembly, at least every 7 days, and after events or alterations. It needs a written report.
  • Pre-use check. Done by the person about to use the tower, before each shift and after a move. The law doesn’t ask for a record, but many sites log it.

The component check is often skipped because the parts look fine in the delivery bag. It is the easiest stage to catch a bent frame or a broken clip, before it ends up in a built tower.

When Your Scaffold Tower Must Be Inspected

HSE says every tower needs inspecting after assembly and at suitable intervals. For construction work with a fall risk of 2m or more, the law sets those intervals at no more than 7 days. Here is what triggers each inspection.

After assembly. Inspect the tower before anyone uses it. This applies every time it goes up, even if the same crew built the same tower last week.

At least every 7 days. Repeat the inspection at least weekly while the tower stays up. Seven days is the limit, not the target. Your risk assessment may call for more frequent checks on busy or exposed sites.

After adverse events. High winds, heavy rain, snow or frost can all affect a tower and the ground under it. So can a strike from a vehicle, plant or a pallet truck. Inspect again before anyone climbs.

After alterations. Changing the platform height, adding a lift, removing a brace or taking off guardrails to pass materials up all count as alterations. Inspect again before use.

Before each use. Users run a quick visual check before climbing. It doesn’t replace the formal inspection, but it catches damage between inspections.

Treat Static and Mobile Scaffold Towers Differently

A static tower stays in one place. Inspect it before first use, every 7 days and after bad weather or changes.

A mobile tower moves, so its risks change. HSE says a new inspection and report is not needed every time a tower moves to a new spot on the same site. A new inspection is needed if guardrails or other parts had to come off to move it, or if anything during the move could have affected its safety. After every move, users should still run a pre-use check: re-level the base, relock the castors and reset the stabilisers.

HSE sets clear rules for moving a tower. Lower it to 4m or less, clear all people and materials, check overhead for power lines and other obstructions, and check the ground is firm with no holes. Push or pull from the base only. Never move a tower in windy conditions.

Check Before You Use a Tower Someone Else Built

On multi-trade sites, crews often use a tower another team built. Before you climb, find the current inspection record and check it is less than 7 days old. Look at the tag. If there is no record, or the tower looks different from what the record describes, treat it as uninspected until a competent person has checked it.

Choose a Competent Person to Inspect Your Scaffold Tower

There’s no single qualification named in law. A competent person has the training, knowledge and experience to know what a correctly built tower looks like and to spot defects.

For mobile towers, the usual standard is PASMA training. Operatives with PASMA Towers for Users can build and inspect standard single-bay towers made to BS EN 1004-1. Managers and supervisors who don’t build towers can take PASMA Towers for Managers, which covers inspecting standard towers. Stair towers, linked towers, cantilevered towers and bridged towers are built to BS 1139-6 and need extra training to inspect.

Get written proof of each inspector’s competence and keep it with your site records. Keep the team small. Two or three trained inspectors using one form give consistent results. For complex builds, such as lift shaft towers, linked towers or long multi-floor jobs, use an independent inspector.

The 9-Point Scaffold Tower Inspection Checklist

Work from the ground up with the manual in hand. The manual lists every part and where it goes, so compare the tower against it rather than against memory. HSE warns that towers can collapse if parts are missing.

The nine points below follow PASMA’s inspection checklist for standard mobile towers. If the answer to any question is no, the tower is not safe to use.

  1. Are the ground conditions suitable, with all castor brakes locked and wheels touching the ground? The floor must be firm and level, with nothing packed under any part. Castors should turn freely when unlocked and hold firm when locked. A wheel lifted off the floor means the tower is not level.
  2. Is the tower level and upright, with the adjustable legs set correctly? Check with a spirit level in both directions. Legs must be within their marked limit and must not be wound out to gain extra height.
  3. Is the tower stabilised as the manual shows? Stabilisers or outriggers must be fitted wherever the manual asks for them. Clamps should be tight and the feet should sit firmly on the floor. Tied towers need ties at the spacing the manual gives.
  4. Are the horizontal and diagonal braces in the right place and secure? Every brace in the manual must be there, with its claws latched. A missing diagonal brace is one of the most common faults on towers that have been up for a while.
  5. Are the frames the right size and type, with all locking clips secured? Frames should sit straight with no bends, cracks or dents. Every spigot clip must be locked. Parts from a different maker should never be mixed in.
  6. Are the platforms in the right place, with trapdoors over the ladder and wind locks engaged? Platforms should be hooked on fully. Look for splits, warping and sagging. Trapdoors must open and close properly.
  7. Do all working platforms have double guardrails on every side? The top rail must be at least 950mm above the platform, and gaps between rails must not exceed 470mm. Most towers fit the top rail at around 1m. Check every rail is locked tight.
  8. Are the toe boards fitted correctly? Toe boards should run around the full edge of every working platform, with no gaps at the corners.
  9. Is the tower the right height for the task? Nobody should need to stretch, lean over the rails or stand on anything to reach the work. If they do, the tower must be rebuilt to the right height. Working out what size scaffold tower you need at the planning stage avoids this.

Finish by checking the access. Built-in ladders or stairs must be complete and undamaged, and users must climb inside the tower only. Make sure the tag is fixed at the access point, the frame labels are readable and the manual is on site.

Adjust the Inspection to Your Scaffold Tower Type

Some towers need extra checks on top of the nine points, because the types of scaffolds used on site differ in how they lock, fold and stand.

  • BoSS standard tower: check the spigot clips, brace hooks and wind locks closely.
  • AGR tower: check the guardrail units are locked in place, or removed, as the manual says.
  • GRP scaffold tower: look for cracks, surface damage and dirt build-up that could carry current.
  • Stair tower: check the treads, handrails and stair fixings.
  • Mi Tower: check the folding hinges and locking catches.
  • Room Mate tower: check the hinge locks and that the brakes hold on smooth floors.
  • Lift shaft tower: check the fit to the shaft, the supports and the gaps at the edges.
  • Narrow scaffold tower: check the leg settings on steps and the stabiliser footing.
  • High clearance tower: check the base bracing and the clearance over obstructions.

Record Each Scaffold Tower Inspection in Writing

Construction work with a 2m fall risk needs a written report after every formal inspection. Schedule 7 of the Work at Height Regulations lists what goes in it. You can use the table below as the basis of your site form.

Report detail What to write
Who it’s for Name and address of the person the inspection was for
Location Where the tower stands
Equipment Description of the tower, such as make, model, tower ID and platform height
Date and time When you inspected it
Risks found Any defect that affects safety
Action taken Repairs or parts replaced
Further action Anything still needed
Inspector Name and job title

The inspector must finish the report by the end of the working period and give a copy to the person it was done for within 24 hours. Keep it on site until the work ends, then keep it at an office for three months.

Pick a format that suits your site. Pocket books are quick but easy to lose. Site logbooks stay put. PASMA’s Tower Inspection Record is a tag-style record that meets the legal requirements when it is fixed to the tower and kept afterwards. Digital tools, such as PASMA’s free TowerSure app, store the record with photos, send a reminder when the 7-day inspection is due and let anyone on site scan a QR code on the tower to see its status. If you use paper forms, photograph them as a backup.

Use Inspection Tags the Right Way

A tag system gives everyone on site an instant answer to one question: can I use this tower? The tag holder is fixed at the access point, at eye level, so nobody can climb without seeing it.

The usual set-up has two states. A green insert, signed and dated by the inspector, shows the tower is safe to use until the next inspection is due. A red or “do not use” tag, or an empty holder, means stay off. Check the date on a green tag every time. An insert older than 7 days means the tower is overdue for inspection, even if it looks fine.

Reading a scaffold tower inspection tag

The tag holder sits at the access point so nobody can climb without seeing it.

SAFE TO USE

Tower ID
Inspected on
Inspector
Next due

Green: check the date. If it is more than 7 days old, the tower is overdue and must not be used.

DO NOT USE

Tower ID
Date
Reason
Reported by

Red or empty holder: stay off the tower until a competent person has fixed and passed it.

 

Common Faults Found During Scaffold Tower Inspection

Most failed inspections come down to the same few faults. Knowing them helps inspectors know where to look first.

  • Missing or loose diagonal brace. The tower can sway or twist under load. Refit it from the manual and inspect again.
  • Stabiliser foot off the floor. The tower can tip, especially when moved or loaded on one side. Reset and clamp the stabiliser.
  • Castor brake not locked. The tower can roll while someone is on it. Lock all brakes and brief the users.
  • Packing under a leg. Packing can crush or slip. Remove it and re-level with the adjustable legs.
  • Guardrail or toe board removed. This creates a fall risk and a falling objects risk. Refit it before anyone uses the tower.
  • Wind lock not engaged. The platform can lift in wind or when knocked. Engage and check the locks on every platform.
  • Split or warped platform. It can fail under load. Take it out of use and replace it.
  • Parts from different makers. Clips may not lock. Replace them with matching parts.
  • Tower built above the manual’s height limit. It becomes unstable. Lower it or change the tower type.

Act Fast When a Scaffold Tower Fails Inspection

Follow these five steps in order.

What to do when a scaffold tower fails inspection

A failed tower stays out of use until it passes again.

1Stop work

Clear the tower and stop anyone climbing.

2Tag it

Fix a do not use tag at the ladder. If you can’t fix it straight away, barrier the tower and report it to the site manager.

3Record it

Note the defect in the inspection report.

4Fix it

Use only compatible parts from the same maker.

5Inspect again

A competent person must pass the tower before anyone uses it.

 

Towers that come through scaffold tower hire should never get an improvised repair. Call the supplier for a matching replacement part.

Check Height Limits During Every Scaffold Tower Inspection

Never build above the maker’s height limit. BS EN 1004-1:2020 covers freestanding towers up to 12m indoors and 8m outdoors. Your manual may set a lower limit.

Added height can change stabiliser needs, so treat any extra lift as an alteration and inspect again. The maximum height of a scaffold tower depends on whether it stands indoors or outdoors, its base width and the stabilisers fitted.

Towers built too tall for the task also cause problems, as they need more stabilising and take longer to inspect. Match the tower to the job before it arrives.

Build Scaffold Tower Inspections into Your Site Routine

Inspections only work if they happen every time. Keep the system simple enough that it doesn’t depend on one person remembering.

Tie the 7-day inspection to something that already happens weekly, such as your site meeting or shift handover. Give every tower a reference number and keep a simple register with its location and next due date, or let an app track it for you. Store a laminated copy of the checklist in the manual wallet on the tower.

Brief everyone who climbs on the pre-use check and make sure they know to report damage straight away. Plan for long hires too. A four-week hire means at least four formal inspections, so build that time into your programme.

Most inspection failures trace back to the build. Crews who follow the correct order for [how to erect a scaffold tower] [link to the erect article once live] usually hand over a tower that passes first time.

Scaffold Tower Inspection FAQs

How often does a scaffold tower need to be inspected?

After assembly, before first use, then at least every 7 days on construction work where someone could fall 2m or more. It also needs inspecting after any alteration or event that could affect its safety, such as high winds or an impact.

Does a tower need re-inspecting every time it moves?

No. HSE says a new inspection is not needed each time a tower moves on the same site. Inspect again if parts had to be removed to move it or the move could have affected its safety. Users should always run a pre-use check after a move.

Who can sign off a scaffold tower inspection?

A competent person with the training and experience to spot defects. For standard mobile towers, that usually means someone with PASMA Towers for Users or Towers for Managers training.

Does a tower under 2m need inspecting?

Yes. Any tower whose safety depends on how it was built must be inspected after assembly and at suitable intervals. The 2m fall height is what triggers the 7-day cycle and written report for construction work.

How long should inspection records be kept?

Keep the report on site until the work is complete, then at an office for three months.

Is a tag on the tower enough?

Only if the tag record holds all the details Schedule 7 asks for and is kept afterwards. A simple “safe” tag without those details shows status but doesn’t replace the written report.

Hire Scaffold Towers Near Your Site

We deliver nationwide from Essex. Next-day service covers major UK cities, including Manchester, Birmingham, Leeds, Liverpool, Bristol, Nottingham and Leicester.

Book the Right Scaffold Tower for Your Next Job

The right tower is easier to inspect and less likely to fail. Our PASMA-trained coordinators will ask about your height, site and job length. Then they’ll match you with the right tower.

Lakeside Hire holds PASMA, CHAS Gold, FORS, SafeHire and HAE accreditations. Call 01708 866566 to book.